A new aquatic facility is a huge undertaking, and your investment should be designed to serve the community for decades. The more work you do up front to understand your target market and the facility's projected financial performance, the better your decision-making and design process – and the better your end result will be.
Our experts will help you answer all of your questions related to purpose of the facility, costs of indoor and/or outdoor facilities, market demographics, site selection, traffic impacts, as well as facility features and operations, including equipment and water treatment.
How Long Does A Project Take?
Assuming funding is in place, here is a typical schedule:
|
•
|
Preliminary & final design – 4-6 months |
|
 |
•
|
Advertising & bidding – 2 months |
|
 |
•
|
Construction – 10-16 months |
|
 |
|
|
|
|